Completed Project-Xiaoyang Phase II Resettlement House [Back]

1-6号楼工程建成总建筑面积81733.09平方米,地上计容建筑面积71054.17平方米,共建设安置房556套。 The total construction area of Xiaoyang Resettlement Community Phase 1-6 project is 81733.09 square meters, and the floor area is 71054.17 square meters. A total of 556 resettlement houses have been constructed.

Construction of the project started in phases. Construction of Building 6 started in October 2011 and Buildings 1-5 started in September 2012. The construction was completed in October 2016. The construction was completed and accepted in October 2017, and resettlement households were organized for relocation.