Completed Projects-Longteng North Road Phase Five (Qingzhu Road-North Third Ring Road) Road Project [Back]
项目起点与青竹路相接,终点与已建成的北三环路(福建龙州工业园区段)相连,全长2700米,宽40米,概算投资20640万元,分两个道路施工标段和一个高边坡防护施工标,于2013年10月8日开工建设。 Project situation: The starting point of the project is connected to Qingzhu Road, and the end point is connected to the completed North Third Ring Road (Fujian Longzhou Industrial Park Section). The total length is 2700 meters and the width is 40 meters. The estimated investment is 26.4 million yuan, divided into two roads. The bidding section and a high slope protection construction bid were started on October 8, 2013. 管道2100米,约占总量的80%,路基成型1820米,总计完成投资14000万元(含拆迁)。 At present, 900,000 cubic meters of earthwork have been completed, accounting for about 92% of the total, rainwater and sewage pipes are 2100 meters, accounting for about 80% of the total, and the subgrade has been formed at 1,820 meters, with a total investment of 140 million yuan (including demolition). Construction of pavement structural layers on some sections has begun .